This week the class was to go out and survey the University of Wisconsin-Eau Claire campus mall using a Topcon total station (Figure 1) provided by the geography department. In Field Activity 4 (Sunday, February 23rd, 2014), the class performed a distance/azimuth survey. This previously learned method works well in many ways and is quite simple. However, more accuracy is at times needed, and elevation data is also nice to have. Surveying using a total station provides these, at times, desired options. It takes elevation data and is usually more precise than a simple distance/azimuth survey. This however, comes at a cost. This cost is both seen in monetary amounts and in convenience. The total station that was used to complete this activity costs over $4,000. Also, the set up of the total station is much more complicated than the point and shoot method of the distance/azimuth survey.
The class spent the in lab period learning how to set up and operate the total station using a GPS that would be connected via Bluetooth to the total station. The set up involved first learning that the equipment is extremely expensive and should be handled with care, and also that in order for the total station to work, everything needs to be leveled. Properly leveling off the total station can take some time and involves adjusting the tripod legs and black nobs on the total station itself. After the station is all leveled, the GPS needs to be activated and connected via Bluetooth. From here the instructor, Joe Hupy, walked the groups of three through the process of being completely prepared and setting a backsight, which is necessary to collect points and will be further explained in the Methods section.
Each group was to get together and collect their data of the campus mall. From here the groups would be required to upload the data into ArcMap and create feature surfaces similar to Field Activity 2 using surface interpolation. These surfaces should ideally mimic the actual campus landscape.
Study Area:
The newly redesigned University of Wisconsin-Eau Claire campus (Figure 2, Figure 3, and Figure 4) was the area in which the survey was performed. Recent renovations to the campus mall have greatly expanded it. It is now a large open area which includes Little Niagara Creek as a main feature. The weather was a pleasant spring temperature and slightly cloudy; as long as it didn't rain the study could have been performed.
![]() |
This image shows the main portion of the campus mall. As can be seen the image slopes slightly down in one direction toward Little Niagara Creek on the left. (Figure 2) |
![]() |
This image shows another view of the campus from the total station. This is facing the newly renovated student center and shows the downward slope towards Little Niagara Creek. (Figure 3) |
![]() |
This is a backwards view from Figure 2 above. It shows one of the higher flatter areas of campus. It can be seen that the campus mall is new by looking at the freshly planted trees. (Figure 4) |
Methods:
The group obtained all of the needed equipment from the geography lab and set out to the center of campus to begin collecting data. The total station was set up and leveled off as was shown in the learning session, and the study area was defined. How the study area was defined is a group member took four flags to place at each corner of the approximate hectare that was to be established. The hectare was defined by using a pace count (see Field Activity 5) and turning approximately 90 degrees in order to get a square 100 meters. This wasn't exact as there are parts of campus that are too narrow because of buildings to have an exact 100 meters across.
The group then connected the GPS to the total station and collected an occupy point. The occupy point is the point directly where the station is placed when it is collecting. It is taken by simply taking a location using the GPS, in this case the mapping grade GPS took an average of twenty points to calculate the occupy point. Referencing the occupy point is key in the total station being able to place the points it measures out in space. From here the group began to set the backsight.
The backsight is required in order to begin taking any points. A backsight involves taking an azimuth measurement manually and then firing the topcon laser into the total station reflector (Figure 5), which is how points are collected. This allows the total station to calculate the azimuth of the direction it is facing, which it cannot do without manually setting a backsight. The azimuth of the backsight was just measured with a compass. This seems like a simply process, however the group had problems getting the total station to measure out the backsight. As it turns out, the total station is a delicate machine and needs to have the firing laser faced a certain direction on the station. Once the laser side of the machine was flipped around, the total station began working exactly as it should.
Approximately 130 points were gathered in total. After the collection was finished, the equipment was packed up and the points were brought into Excel as a text file. From there x and y coordinates (using UTM as the data was gathered in UTM zone 15) were converted into a feature with an elevation z. Spatial interpolation (kriging method) was then run in order to create a surface that represents the terrain of campus (Figure 8).
The surfaces created from various groups was then compared (Figure 9) to see the various differences in study area and to see if there were any irregularities in any surveys.
Discussion:
As the surfaces are observed, there are several things that stand out. The surfaces created by the different groups for the most part accurately represent the slight downward slope of the campus surface to the creek. However, in the surface created in Figure 8 the creek appears to be somewhat unnatural as it doesn't continue upstream as it actually does in the real world. This is likely due to a lack of taking points to the edge of the survey area along the side of the creek. Next time this survey is done, the groups will need to be sure to take points to the limits of the survey area in a case like this in order to better represent natural features.
A real world feature well represented in the surface in Figure 8 is the area directly surrounding the creek. The group was sure to take more points along the areas in which the change in elevation was greater to try and ensure that the data would be as accurate as possible. Due to this it appears that the areas alongside the edge of the creek in Figure 8 are well shown. However, the creek does have a noticeable irregularity. There is an area of higher elevation along the creek which appears extremely unnatural. This is due to a bridge being in that area and the land sloping up to greet the bridge. The bridge could be better represented if some other method to gather data around it or to represent it was used. In the surface in Figure 8, the bridge simply appears to be an error, so it's important to mention what it actually is.
Conclusion:
Earlier in the semester, the class used a distance/azimuth survey method to survey an area. This past week, the class stepped it up a level and used a total station to survey a study area. The total station, while more complicated to set up and much more sensitive, provides a higher level of precision and also provides elevation data which is extremely useful in many cases. Through the processes of this lab, the class learned how to properly deploy a total station, gather points, and bring them into a GIS in order to analyze them for accuracy. This activity also took a large amount of group work and collaborating to make surveying work well. Thankfully the various groups have gotten good at working together and this greatly aided in making the total station survey run smoothly.